14.1.4 Job Net Operations and Actions

This section describes the job net operations and the actions following the job net operations. The following operations can be executed for job nets.

Cancelled

Cancels the job net being executed.

Start

Starts the job net immediately. The job nets will be executed from the first one.

The configuration information used at the startup of a job net including the jobs (child or linked job nets) with the Valid only on startup days settings varies depending on the status as described below.

Note

The message event occurrence status will not be cleared after the startup operation. For details, see "14.4 Message Events and Job Net Actions".

Restart

Restarts the job net. Basically, execution of jobs starts from the abended job. It is possible to specify the first job to start by setting the restart point.

For details, see "Restarting job nets".

Pause

Pauses the job net. The paused job net cannot be executed even if the execution conditions are satisfied. If the job net belongs to a group, the group will be in the executing status.

Continue

Cancels the paused status of the job net. When resumed the job net acts as follows.

Disable

Disables the job net. The disabled job net is considered to be pseudo-normal when the startup time has come and will be skipped. When the execution conditions are satisfied while the job net is being paused, the job net will be considered to be pseudo-normal and skipped when disabled.

When the job net belongs to a group, the succeeding job net will be executed when the disabled job net is skipped.

If a carried over job net is disabled, the schedule will be re-created upon the disable operation and the job net will be disabled while the next scheduled startup date and time is specified.

Enable

Cancels the disabled status of the job net. When the disabled status is cancelled after the startup time of the job net, it will be terminated normally. The job net has already been skipped and will not start unless started manually.

When enabled, the job net acts as follows.

Confirm

Brings the previously-abended job nets (including cancelled job nets when Check canceled option is checked in the Define Jobscheduler Startup Parameters window) to the confirmed status. Confirmation is enabled when Validate job net confirmation is selected in the Advanced Settings for Verification window (which is displayed by clicking the Advanced Settings button in Verification at error occurrence in the Use function1 sheet of the Define Jobscheduler Startup Parameters window). When the Validate job net confirmation option is selected and the job net remains in an abended state, the job net will not be executed even if the next execution conditions are satisfied. After confirm operation on the abended job net, the job net will be executed when the next execution conditions are satisfied.

Note that to enable verification with respect to canceled job nets, it is necessary to select Check canceled as well as Validate job net confirmation in the Advanced Settings for Verification window.

Reinstate

Cancels the execution results of the job nets (Completed, Pseudo-normal, Abended or Cancelled) which have been executed for the day. This operation is available only when Start only when message event has occurred is selected in the Job Net Properties window and Once in a day is checked.

After cancellation, the job net will be in the waiting status and be able to wait for a message event occurrence as the execution condition again. If Scheduled start time is specified, the scheduled startup date and time will be set for the day. If not specified, the current date will be set.

If Scheduled start time is specified and the reinstate operation is executed after the estimated start time, the job net will be in the waiting status upon execution of the reinstate operation. In such cases, delay monitoring via the delay monitoring specifications for the job or job net will not be carried out. When a message event occurs after the reinstate operation, the job net will be started and be in the executing status.

Revoke

Cancels the carried over status of the job net.

The scheduled startup date and time will be re-scheduled to the next ones upon execution of the revoke operation and the job net will be in the waiting status.

If the next scheduled startup date and time is passed while in the carried over status since the message event has not occurred, the execution reject message "refused" will be output to the log file jobdb*.log. The job net will remain in the carried over status, and the execution schedule for the current day will be ignored. The scheduled startup date and time will be re-scheduled to the next ones upon execution of the revoke operation and the job net will be in the waiting status.

Start with variable parameters

When a job net receives a variable parameter, it will start up with a preset variable replaced by the variable parameter.

Refer to "7.4 Starting a Job Net with Variable Parameters" for details.

Restarting job nets

When restarting job nets, jobs to be executed can be selected as follows.

When a job net contains jobs (child or linked job nets) with the Valid only on startup days setting, and the status of an abended or canceled job net becomes "Confirmed" since the "confirmation" operation for the abended or canceled status is enabled, it is restarted with the configuration information shown in the Previous process result sheet of the Monitor Job Net window.