When the day change time comes or when the Systemwalker Operation Manager server is started after the day change time, schedule for the current day will be created. This section describes how job nets or groups are scheduled depending on their conditions when creating schedules.
Schedules will be created again when the day change time is changed. However, it is not desirable to change the day change time during job operation, since it may affect the job operations because a group cannot be scheduled upon re-scheduling once it is started, or because the relationship between the scheduled startup times may be changed resulting in changes in the execution days. If the day change time is changed, already occurred message events are cleared that belong to the job net for which Once in a day under the Start only when message event has occurred check box has been specified.