9.2 A Schedule by Dates Project that has Exceeded the Number of Stored Generations of Schedule Information is Not Deleted

Applicable versions and levels

Action

Points to check

Did you create the schedule by dates project using the Systemwalker Operation Manager client or jobschsetproject command?

Cause

Schedule by dates projects created manually are not targets of the Schedule Distribution/Master Schedule Management functions, therefore, if no schedule by dates project was automatically created on the same day, the schedule by dates project is not deleted even if the number of stored generations of schedule information is exceeded.

Action method

If a project that was created manually is no longer needed, delete it manually.