9.3 Because of Manual Startup, the Job Net that should have Completed is Scheduled and then Restarted

Applicable versions and levels

Action

Points to check

Did you perform a start operation for an unapplied job net?

Cause

An unapplied job net that is waiting for the completion of a job net of the previous day is scheduled for when the job net of the previous day completes.

Action method

Perform the disable operation after the unapplied job net for which the start operation was performed completes its startup.

To change the execution status from "Disabled" to "Completed" of a job net after the scheduled start time has elapsed, perform the enable operation at the scheduled start time or later.