Top
Systemwalker Operation Manager Troubleshooting Guide
FUJITSU Software

9.1 Creation of Schedule Information Fails

Applicable versions and levels

Action

Points to check

Is there already a project with the same name as the project (project name + mmdd) for the schedule information that failed to be created?

Cause

If the number of the times that schedule information is created in a year is less than the number of generations that store schedule information as specified in the Master Schedule Management Environment Setup dialog box, there may be schedule by dates projects with the same date and month but different years.

Alternatively, there is a manually created schedule by dates project with the same name.

Action method

Manually delete old schedule by dates projects with the same name.

If there are schedule by dates projects with the same date and month but in different years, reduce the number of generations specified in the Master Schedule Management Environment Setup dialog box so that the old schedule by dates project is deleted automatically.

If you ensure that the schedule information created in a year exceeds the number of generations that store schedule information as specified in the Master Schedule Management Environment Setup dialog box, any schedule by dates project with the same name will automatically be deleted. You can increase the schedule information to be created by registering, in the project, job nets to be started on different startup days.

Refer to the following manual for information on the number of generations that store schedule information: