Applicable versions and levels
Windows versions: V5.0L10 or later
Solaris versions: 5.0 or later
Linux versions: 5.2, V10.0L10 or later
Linux for Itanium versions: V12.0L10 or later
HP-UX versions: 5.1 or later
AIX versions: 5.1 or later
DS versions: V20L10
Action
Cause
In the Systemwalker Operation Manager client, a time axis from 00 minutes to 25 hours is displayed for the display start time (if this was omitted, this will be the day change time instead). If the day change time or display start time is specified not using 00 minutes, for example xx hours 30 minutes, the Gantt chart switches at a different time to the day change time.
Action method
If an unintended time was specified as the display start time, correct the specified display start time. The display start time can be set/checked in the Display Start Time Setup window, that is displayed by selecting Display Start Time from the View menu in the Systemwalker Operation Manager window. Refer to the Online Help for details.
Note that the schedule processing will be performed on the specified day change time. The date does not change according to the timing of the Gantt chart switch. Schedule processing is not performed either.