Applicable versions and levels
Windows versions: V5.0L10 or later
Solaris versions: 5.0 or later
Linux versions: 5.2, V10.0L10 or later
Linux for Itanium versions: V12.0L10 or later
HP-UX versions: 5.1 or later
AIX versions: 5.1 or later
DS versions: V20L10
Action
Points to check
Was the Valid execution time option set for the succeeding job net?
Cause
If the Valid execution time option has been set for the succeeding job net, the succeeding job net will start at the point when all the following conditions apply, regardless of whether or not the Wait for startup time option has been set (*1) for the succeeding job net:
The preceding job net has ended normally, and
The scheduled start time for the succeeding job net has arrived, and
A message event that the succeeding job net is waiting for is generated (*2)
*1: This option can be set only when the job net waits for message events. *2: Only a job net that waits for message events.