The procedure for building a PRIMECLUSTER cluster is shown below:
building procedure | Work item | Execution Node | Required/Optional | Manual reference location* |
---|---|---|---|---|
(1) | All nodes | Required | CF 2.1 CF, CIP, and CIM configuration | |
All nodes | Required | CF 8 Shutdown Facility | ||
5.1.3 Initial Setup of the Cluster Resource Management Facility | All nodes | Required | CF 4.3 Resource Database configuration | |
(2) | 5.2 Setting Up Fault Resource Identification and Operator Intervention Request | 1 node | Required |
* The PRIMECLUSTER manual names are abbreviated as follows:
CF: PRIMECLUSTER Cluster Foundation (CF) Configuration and Administration Guide
Note
Be sure to configure GDS after initializing the cluster.