4.4 Q: How Do I Display a Schedule in the Gantt Chart?

Applicable versions and levels

A

Defining an execution time for a job net makes it a scheduled job net. If a job net is scheduled to run on the current day, it will be displayed in the Gantt chart even if it has not yet started running.

On V11.0L10 and 11.0 or later, a scheduled job net is displayed in the Gantt chart before it starts running if Start only when message event has occurred and Once in a day are selected and Scheduled start time is specified under Execution condition in the Standard information tab of the Job Net Properties window.