Applicable versions and levels
Windows versions: V5.0L20 or later
Solaris versions: 5.0 or later
Linux versions: 5.2, V10.0L10 or later
Linux for Itanium versions: V12.0L10 or later
HP-UX versions: 10.0 or later
AIX versions: 10.0 or later
A
V13.8.0 or later
You can set job net startup days in the Startup Days(Other) window as follows:
Example: Setting the first, third, and fifth business days of each month as startup days
Basis settings: Business days
Selected business days: First, third, and fifth business days
V13.0.0 or later
Open the Job Net Properties window and click the Startup days tab. You can then set the business days as shown below.
Example: Setting the third business day of each month as the startup day
Basis settings: Business days
Selected business days: Third business day
V12.0L10, 12.1, and V12.0L11 or earlier
You can select working days in the number of shifted days when setting startup days.
Use the following procedure to enter settings:
Open the Job Net Properties window and click the Calendar tab. Then add the selected calendar from Unselected calendar to Selected calendar.
Open the Job Net Properties window and click the Startup days tab. Then enter settings as shown below.
Example: Setting the third business day of each month as the startup day
Basis settings: Monthly
Monthly standards: 1
Shift process: Shift to next day
Shifted days: "Business days-1"
Working days: Check
In the Startup Days window, ensure that the startup day has been set as intended.