The procedure for building a PRIMECLUSTER cluster is shown below.

Work item  | Execution Node  | Required/Optional  | Manual reference location*1  | |
|---|---|---|---|---|
(1)  | ||||
All nodes  | Required  | CF "1.1 CF, CIP and CIM configuration"  | ||
All nodes  | Required*2  | CF "Chapter 7 Shutdown Facility"  | ||
5.1.3 Initial Setup of the Cluster Resource Management Facility  | All nodes  | Required  | CF "3.3 Resource database configuration"  | |
(2)  | All nodes  | Optional  | "Machine Administration Guide"  | |
(3)  | All nodes  | Required  | ||
(4)  | 5.4 Setting Up Fault Resource Identification and Operator Intervention Request  | 1 node  | Required  | 
*1 The PRIMECLUSTER manual names are abbreviated as follows:
CF: PRIMECLUSTER Cluster Foundation (CF) Configuration and Administration Guide
*2 When configuring a single node cluster, it is not necessary to setup the shutdown facility.