Holiday calendars include a default calendar called "SYSTEM_ CALENDAR" that has been registered in the Management Server in advance. The holidays that have been set up in the "SYSTEM_CALENDAR" are displayed as holidays in the date field of the monthly schedule of the operation schedule.
In addition, a date change time (the time at which date changes and new day begins) can be set up in the system calendars. The date change time at installation is 0 hours 0 minutes.
If you want to use multiple holiday calendars, you can add holiday calendars at your discretion.
Use swrba_holimport command to register a holiday calendar or use swrba_change_systime to change date change time.
This command registers holiday calendar information. Use a calendar definition file with this command to register holiday calendar and make sure to keep a backup of the calendar definition files you register.
swrba_holimport -ent calendar definition file
This command outputs holiday calendar information. For the "SYSTEM_CALENDAR", this command also outputs the date change time.
This command changes a date change time.