J.3 Test

When using the Remote Power Distribution Unit, check that the RPDU shutdown agent is correctly set by using the following procedure:

  1. Shut down a standby node. For SPARC Enterprise M4000 and M5000, shut down all partitions. For SPARC M10, shut down all domains.

  2. In the Remote Power Distribution Unit Web interface, connected to the main power and redundant power of the standby node, turn the outlet number to which the standby node is connected OFF.

    1. Enter the following URL from a browser such as Microsoft Internet Explorer or Mozilla Firefox to connect to the Remote Power Distribution Unit Web interface.

      http(s)://<IP address>

      *<IP address> is the IP address specified for the initial setting for the Remote Power Distribution Unit.

    2. If a security warning message is displayed, click OK or Yes.

    3. The Login page is displayed. Enter the created pcl user and password for login.

    4. From the Remote Power Distribution Unit Web interface menu, display the Home page.

    5. The power status for each outlet is displayed in the Outlets list. Click OFF for the outlet number to which the cluster node is connected.

      If you cannot click OFF, the settings of "System Permission" and "Outlet Permission" for the pcl user may be insufficient.

      See "J.2.3 Creating a User for Shutdown Facility" to review the permission setting for the pcl user.

    6. A dialog box for checking the operation is displayed. Click OK, and then the outlet power turns OFF.

    7. From the Remote Power Distribution Unit Web interface menu, select the Home page to update the screen. Check that the outlet number of the outlet, which was turned OFF in step 5 and 6, is now OFF.

  3. Execute the following command in the operation node.

    # /opt/SMAW/SMAWsf/bin/sfrpdupoweron -p CF-node-name-of-the-standby-node

    If the following message was output, the settings of "System Permission" and "Outlet Permission" for the pcl user may be insufficient.

    See "J.2.3 Creating a User for Shutdown Facility" to review the permission setting for the pcl user.

    outlet power-on failed.

  4. Check that the outlet number on which its power was turned OFF in step 2, is now ON. If not, review the setting for the shutdown facility.

  5. For SPARC Enterprise M4000 and M5000, perform step 2 to 4 on all partitions used the RPDU shutdown agent.

  6. Start the standby node.

  7. After starting the standby node, shut down the operation node. For SPARC Enterprise M4000 and M5000, shut down all partitions. For SPARC M10, shut down all domains.

  8. Turn the power of the outlet number to which the operation node is connected OFF in the Remote Power Distribution Unit Web interface.

  9. Execute the following command on the standby node.

    # /opt/SMAW/SMAWsf/bin/sfrpdupoweron -p CF-node-name-of-the-operation-node

    If the following message was output, the settings of "System Permission" and "Outlet Permission" for the pcl user may be insufficient.

    See "J.2.3 Creating a User for Shutdown Facility" to review the permission setting for the pcl user.

    outlet power-on failed.

  10. Check that the outlet number to which its power was turned ON in step 8 in the Remote Power Distribution Unit Web interface. If not, review the setting for the shutdown facility.

  11. For SPARC Enterprise M4000 and M5000, perform step 8 to 10 in all the partitions where the RPDU shutdown agent is used.

  12. Start the operation node.