4.8.1 When the Termination Processing Job Net is Started, it does not Start even when the Next Execution Time Arrives

Applicable versions and levels

Action

Cause

According to the specification, the starting of a new job net is suppressed at the point when the termination processing job net was started.

Action method

To start the job net at the next execution time, restart the Systemwalker MpJobsch service.

When the termination processing job net is complete, a completion shutdown exit will be started. The completion shutdown exit provided in the installation starts the "shutdown.exe" to shut down the server after the Systemwalker MpMjes service and Systemwalker MpJobsch service were stopped.

If the termination processing job net ended abnormally or was canceled, an abend shutdown exit will be started. The abend shutdown exit does not exist when Systemwalker Operation Manager is installed.

To restart the service automatically if the job net ended abnormally or was canceled, create an abend shutdown exit based on the completion shutdown exit.

Note that, if processing to restart the service is added to the abend shutdown exit, the service will be restarted each time the termination processing job net ended abnormally or was canceled.

Also, refer to the following manual.