Top
Systemwalker Desktop Patrol V14g Operation Guide: for Administrators
Systemwalker

9.1.3 Set Security Auditing

This section describes how to set security auditing.

The procedure for setting security auditing is as follows:

Please perform this setting by the system administrator. The section administrator need not set.

  1. Select [Programs] - [Systemwalker Desktop Patrol] - [Environment Setup] - [Management Ledger Settings] from the start menu of CS.

    The [Management Ledger Settings] window will be displayed

  2. Select the [Set Security Auditing] tab.

    The following window will be displayed

  3. Set security auditing schedule and auditing result saving period.

    Set the following information and click the [OK] button.

    Item Name

    Descriptions

    [Not Start Security Auditing by Schedule]

    Selected when not starting security auditing by schedule.

    [Start Security Auditing by Schedule]
    (Initial Value)

    Selected when starting security auditing by schedule.

    [Scheduler Setting]

    [Execution Date]

    Set the date for performing security auditing.

    Single-byte numbers only can be set.

    [Start Time]

    Set time for performing security auditing.

    [Rectification Period]

    Set number of days of rectification period.

    Single-byte numbers from 0 to 6 can be set. When 0 is specified, the rectification period does not exist, and the security auditing is performed only on the date set by schedule.

    Please set rectification period as one excluding the startup date (number of days).

    For example, when specifying as starting on the first day of each month and setting rectification period as 5 days, it will be started during the first day to the sixth day of each month.

    Besides, the execution date and rectification period should be specified in the same month.

    [Retention Period for Auditing Result]

    Select the auditing result saving period from the following options.

    • 3 months

    • 6 months

    • 1 year

    The initial value is 6 months.

    Please set the auditing result saving period as one excluding this month. For example, if the retention period is set as 3 months, and it is July 15th currently, the auditing result of April, May and June will be reserved.

    The auditing result exceeding the retention period will be deleted automatically.

    The information is set.