ServerView Resource Orchestrator Cloud Edition V3.1.0 User's Guide for Infrastructure Administrators (Resource Management)

17.9.2 Operation

The methods for operating physical servers after usage changes are as follow.

Perform the procedure given in "17.9.1 Configuring L-Servers for Usage Change" before performing any operations.

Point

  • Usage cannot be changed, while the L-Server is stopped temporarily during L-Server restart.

  • When power operation has been performed directly on the physical server using the ROR console or commands, without performing power operation of the L-Server, the L-Server which was last operated will start.

  • If the last L-Server that was operated has already been started on another physical server, its status will change so there is no boot disk and it will fail to start.